EOT-CRANE CERTIFICATION - OUR CRANE SPECIALIST WILL ALWAYS PUT YOUR SAFETY FIRST

Certification Is the Guarantee for Safety, Quality and Liability

We Lemmens Crane Systems are having and using our Know How in partnership with the EKH association, meaning that you will be sure that we respect the strict quality standards for Inspection, Testing and Certifying your Hoisting Equipment / EOT-Crane Systems.

YES, of course it is also integrated inside our joint venture partners.

 

EKH Association

We have available EKH-Accredited Qualified Service Engineers, for testing and certifying Your Hoisting Equipment / EOT-Crane systems.

Load Testing

Experienced specialists will inspect and certify Your new and existing Hoisting Equipment / EOT-Crane Systems. We will always put Your safety first.

Quality Standards

To provide quality services we are ISO, certified since 1995 with integrated SHE-Policy and EKH certified since the early days.
All Lemmens Crane Systems Hoisting Equipment’s / EOT-Crane Systems are CE certified.

Certification ISO Functionality

Input


  • Input
  • Building site instructions
  • Assembly drawing
  • Work Voucher
  • Inspection plan / Requirements
  • Materials list
  • Conducting Test

Output


  • Job – Card
  • Inspection Reports
  • Works Voucher
  • Documentation file

Functionality


Erection and after sales Management will take care of the assembly, erection and certification, Also arranges after sales services of cranes.

For this purpose, information about the lay-out and measurements is collected in advance and the planning and execution of the erection is discussed. All agreements about safety and security will be recorded in writing in the minutes of meeting. These will be recorded part by part in the project file. If safety risks can be identified during assembly, Health Safety plan will be designed for the engineers. Necessary personal protection equipment will be handed out.

After planning assembly will be commenced when the produced parts have been delivered to the project location and when the engineers have been assigned by Planning. All employees will receive instructions regarding bottle necks during execution and the safety issues conform the Health Safety plan. Before assembly these will be completed with construction site instructions, which will be discussed with the client in advance. In the event of a calamity, the local First Aid trained person will be called in to coordinate the necessary aid. The project leader will register the accident.

The Manager checks the progress of the jobs and takes care of solving bottle necks during execution. All approved changes will be recorded in writing on the work drawings. Information regarding materials used and hours worked will be recorded on the Form-Job card.

Before Handover of the Crane the required Inspection procedure will be followed, after that the crane will be handed over to the client. Finally, the Manager will take care that the users manual and the official CE document will be available.

After Service and Inspection carries out services at the client’s location or in the workshop, in accordance with the planning.

The service engineers should tell his inspection format/(EKH) with necessary comments. If any parts need to service or replace, they will do as per contract instruction.

Procedures


O.01  Project planning
O.02 Health Safety plan
O.03 Assembly
O.04 Executing test procedures
O.05 Delivery
O.06 External Calamity
O.07 Hoisting and Lifting Tools-Inspection-Assembly
O.08 Hoisting and Lifting Tools –Repairs
O.09 Hoisting and Lifting Tools – Periodical-inspection

Input


  • Work order
  • Production planning
  • Detailed drawings
  • Price list
  • Cutting list
  • Installation schedule
  • Load Test

Output


  • Work file
  • Progress report
  • Checklists
  • Registration of work hours / time sheet

Functionality


Functionality Product Management executes projects in the workshop, in accordance with the planning. Using the available materials, people and means, they execute the planned projects quickly and efficiently by means of work orders.

Product Management will receive the standard work file from Planning, which contains all important detailed drawings and material specifications. They are responsible for executing the planned work as agreed and for registering all details on the required forms and documents. The necessary materials and parts will be supplied per project by Supply Management.

After completion of every work phase, a check will take place confirm the Quality plan, making use of the appropriate checklists. Work Planning will give support in order to find solutions when technical difficulties occur and will decide which changes should be made. Technical changes will be noted down on the work drawings by production staff and later accounted by the Drawing Office. The project parts will be released for assembly based on inspections using checklists and documents. Differentiation in the planning will be reported to Planning. Details with regard operating times and presence and absence will be recorded for work administration and project progress.

If a calamity or work accident occur during the work performance the First Aid Trained employee will be called in immediately. He/she will take charge until a stable situation has been realised or until an external rescue team has arrived. The accident will be recorded in the accident registration file and given to the Quality Coordinator.

Also, everyone is responsible for the separate collection of the released waste produce and to take care of disposal in accordance with the legislation in force.

Procedures


M.01  Production Management Mechanical/Electric
M.02 Temporary checks
M.03 Release workshop
M.04 Internal Calamities
M.05 Waste
M.06 Workshop Repair